 |
This Shot was taken late
in July 2003
|
|
The little blue building in the background is
a solar lumber kiln that Mary and I built by ourselves in 1990 (with the help of
a big concrete truck for pouring the footings.)
In the foreground men lay the
foundation of a lumber storage barn that should house all the scrap lumber in
the shop, all the stacks of furniture-grade lumber we have had air-drying over
the years and some tools. The barn is to be attached to the old kiln as you can
see in this drawing.
Here's a crude video
clip -- it takes a good minute or more to load,
even with broadband -- of some of the tough excavation the site needed. We hit three kinds of
rock: sandstone (easy), limestone and/or dolomite (harder) and granite (AWFUL)!
The noisy tool is called a "hoe-ram" and called by some people, a "chipper."
They're almost as good as blasting.
Below-left you see the finished holes.
Below-right, the first half of a pour.
|
 |
 |
|
The three sticks of rebar coming up out of the
pour in the pic to the right, above, help to bind the lower half of the pour,
which fills the rough hole, to the upper half. That top half is shaped by one of
those cardboard tubes you see in the photo at the top of this page.
Below, the 20-foot tall 6" X 6"s are going up.
|

| In the
picture above, Mark, with his back to you, has his left hand on a half-built
retaining wall. It is just over four feet here and it's now topped out at
nine feet. Made of heavily braced 4" X 6" pressure-treated timbers laid thin
side up and spiked together with rebar. See the massive braces below. |
 |
 |
| This, above, is one of
three pressure-treated 6"X6" diagonal braces. the 4"X 6" uprights lag-bolted
to the 6"X6" serve to stiffen it. |
The close-up,
above, shows a point I designed to vector some of the strength up; to block
the diagonal in place. Is this thing over-built, or what? |
|
You know, civil engineers
are kind of like cops: you can never find one when you need one. Here I've
got a master civil engineer (so much nicer than those impolite ones, I
think) in the family: my son. So where was he when I needed him for this
project? In Iraq! |
 |
Rafters almost done. By
avoiding the use of trusses we got a lot of storage on the third level of
the building. We made the roof taller than the architect's plans in the
drawing. We'll put a
trapdoor and a block and tackle as well as the existing pull-down attic
stairs. |
 |
 |
 |
| Sheathing going on. We'll
Tyvek it for Winter, so that the siding can season. |
Rick cuts tracks for
brackets. ...hot sparks a flyin', fourth of Julyin'.... |
Some of 448 "stickers" for
allowing airflow through the 170 once-inch siding boards. |
| Each of
those pointy black brackets will hold more than 400 lbs. There will be 680
on this floor alone.
It's mid-October 2003 in the shots
above and below and it's getting chilly. Leaves are falling in earnest and
the woods are changing color. |
|
 |
 |
|
Misty morning siding
delivery of the lumber barn's first new-sawn oak. Even though the logs had
some age on them this stuff should dry till spring at least if air-dried. |
Siding for lumber barn
is barn's first load on Oct. 20, 2003. If our
solar lumber kiln were ready we could dry at least half of the siding
there now and get it all up this year. |
This page has gotten too
long. To continue the lumber barn's progress, click
here.
Here's a drawing
of what we intend it to look like. We have made it taller
than Architect Tim Watson wanted. Maybe two feet taller? His proportions were
prettier. Mine are more useful.

|